Research on Step Pre-loading Technology of Anchor Bolts Groups in Gantry Machining Center Installation
-
摘要: 五轴龙门加工中心在现场安装过程中,地脚螺栓安装预紧力导致机床床身变形将影响加工中心的几何精度,而产生的应力分布特性将影响加工中心的精度保持性。论文在分析螺栓预紧模型的基础上,提出了基于最小变形安装误差和均匀螺栓结合面压力分布的地脚螺栓组分步预紧工艺方法,并量化分析了预紧顺序、分步加载预紧步数以及预紧力分配比例对于导轨安装面几何精度、结合面压力分布均匀性以及精度保持性的影响。仿真结果表明,该方法能够实现五轴龙门加工中心地脚螺栓组快速,有效的安装,解决了传统经验安装效率低,精度难以保证的问题。Abstract: In the installation process of five-axis gantry machining center, the machine bed's deformation, resulting from pre-loading force in anchor bolts installation, will affect the geometric accuracy of gantry machining center, and the stress distribution characteristics will affect the gantry machining center's accuracy maintenance. Based on the analysis of the bolt pre-loading model, the step pre-loading method of the anchor bolts is proposed, and the method is based on the minimum deformation installation error and the uniform pressure distribution of the bolts. And how these factors, including pre-loading order, pre-loading steps' number and pre-loading steps' ratio, influence the geometrical accuracy of rail mounting surface, uniformity of the pressure distribution and precision retention of the gantry machining center are analyzed quantitatively. The simulation results show that the present method can realize fast and effective installation of the anchor bolts in five-axis gantry machining center, and it can also solve the problem that the traditional experience method's installation efficiency is low and its accuracy is difficult to guarantee.
-
Key words:
- gantry machining center /
- anchor bolts /
- pre-loading in steps /
- pre-loading force
-
[1] Wang Y Q, Wu J K, Liu H B, et al. Modeling and numerical analysis of multi-bolt elastic interaction with bolt stress relaxation[J]. Proceedings of the Institution of Mechanical Engineers, Part C:Journal of Mechanical Engineering Science, 2016,230(15):2579-2587 [2] 张根保,柳剑.提高国产数控机床可靠性的若干关键问题[J].世界制造技术与装备市场,2014,(1):85-89 Zhang G B, Liu J. Some key problems in improving the reliability of domestic CNC machine tools[J]. World Manufacturing Engineering & Market, 2014,(1):85-89(in Chinese) [3] 胡敏,余常武,张俊,等.数控机床基础大件精度保持性研究[J].西安交通大学学报,2014,46(6):65-73 Hu M, Yu C W, Zhang J, et al. Accuracy stability for large machine tool body[J]. Journal of Xi'an Jiaotong University, 2014,46(6):65-73(in Chinese) [4] Delhomme F, Debicki G. Numerical modelling of anchor bolts under pullout and relaxation tests[J]. Construction and Building Materials, 2010,24(7):1232-1238 [5] Hoang V L, Jaspart J P, Tran X H, et al. Elastic behaviour of bolted connection between cylindrical steel structure and concrete foundation[J]. Journal of Constructional Steel Research, 2015,115:131-147 [6] Van Campen D H. A systematic bolt-tightening procedure for reactor vessel flanges[C]//Proceedings of the 1st International Conference on Pressure Vessel Technology. Delft, Netherlands:Univ. of Tech., Delft, 1969:131-141 [7] Abasolo M, Aguirrebeitia J, Avilés R, et al. Methodology for the optimization of bolting sequences for wind generator flanges[J]. Journal of Pressure Vessel Technology, 2014,136(6):061202 [8] Bouzid A H, Nechache A. An analytical solution for evaluating gasket stress change in bolted flange connections subjected to high temperature loading[J]. Journal of Pressure Vessel Technology, 2005,127(4):414-422 [9] Nassar S A, Yang X J. Novel formulation of bolt elastic interaction in gasketed joints[J]. Journal of Pressure Vessel Technology, 2009,131(5):051204 [10] Alkelani A A, Nassar S A, Housari B A. Formulation of elastic interaction between bolts during the tightening of flat-face gasketed joints[J]. Journal of Mechanical Design, 2009, 131(2):021004 [11] 陈成军,杨国庆,常东方,等.面向结合面密封性能要求的装配连接工艺设计[J].西安交通大学学报,2012,46(3):75-83 Chen C J, Yang G Q, Chang D F, et al. Assembly connection design orienting to sealing performance of joint surface[J]. Journal of Xi'an Jiaotong University, 2012,46(3):75-83(in Chinese) [12] 刘坤,刘文雨.基于ABAQUS的螺栓预紧分析[J].机械制造与自动化,2011,40(2):105-107 Liu K, Liu W Y. Analysis of bolt preload based on ABAQUS[J]. Machine Building & Automation, 2011,40(2):105-107(in Chinese) [13] 王永青,吴嘉锟,刘海波.基于弹性相互作用的大型数控机床地脚螺栓预紧顺序规划[J].制造技术与机床,2015,(8):82-85 Wang Y Q, Wu J K, Liu H B. Anchor bolt pre-loading sequences planning for large CNC machine tools based on elastic-interaction[J]. Manufacturing Technology & Machine Tool, 2015,(8):82-85(in Chinese) [14] 刘海波,吴嘉锟,王永青.地脚螺栓蠕变松弛对大型数控机床几何精度衰退的影响[J].西安交通大学学报,2015,49(9):14-17,140 Liu H B, Wu J K, Wang Y Q. Impact of anchor bolts creep relaxation on geometric accuracy decline of large computer numerical control machine tools[J]. Journal of Xi'an Jiaotong University, 2015,49(9):14-17,140(in Chinese) [15] 杨辉,韩江,褚向前.螺栓联接结构接触应力及结合面刚度影响因素研究[J].机械强度,2015,37(1):128-132 Yang H, Han J, Chu X Q. Bolt coupling structure of contact stress and the influence factors of joint stiffness[J]. Journal of Mechanical Strength, 2015,37(1):128-132(in Chinese)
点击查看大图
计量
- 文章访问数: 260
- HTML全文浏览量: 31
- PDF下载量: 9
- 被引次数: 0