Schedule Model for Project Portfolio Based on Design Structure Matrix
LI Sui-ke, BAI Si-jun, GUO Yu-tao
School of Management,Northwestern Polytechnical University,Xi'an,710073,P. R. China
Abstract:
To improve the enterprise resource utilization and shorten the cycle of the whole project portfolio,a scheduling model based on Design Structure Matrix (DSM) is built. By setting the project activity weight index system and calculating the activity weight for the project portfolio,the constraint relationship between project portfolio information and resource utilization,as the two dimensions of the DSM,are fully reflected in the schedule model to determine the order of these activities of project portfolio. A project portfolio example is given to illustrate the applicability and effectiveness of the schedule model.
Key words:    project portfolio    schedule model    design structure matrix    activity weight index system   
Received: 2013-01-12     Revised:
DOI:
Funds: This paper is supported by National Natural Science Foundation of China under Grant No.71172123;Aviation Science Fund under Grant No.2012ZG53083;Soft Science Foundation of Shaanxi Province under Grant No.2012KRM85;the Funds of NPU for Humanities & Social Sciences and Management Revitalization under Grant No.RW201106
Corresponding author:     Email:
Author description:
Service
PDF(564KB) Free
Print
Authors

References:
[1] Cao Y,Zhang Y J,Zhao R J. Project manage-ment and coordination of distributed coopera-tive product design in a virtual enterprise[J]. International Journal of Plant Engineering and Management, 2004, 9(4):183~191 (In Chi-nese)
[2] Sabatier V, Mangematin V, Rousselle T. From recipe to dinner: business model portfolios in the european biopharmaceutical industry[J]. Long Range Planning, 2010, 43:431~447
[3] Golmohammadi A,Pajoutan M. Meta heuris-tics for dependent portfolio selection problem considering risk[J]. Expert Systems with Ap-plications, 2011, 38:5642~5649
[4] Geraldi J G. The balance between order and chaos in multi-project firms: a conceptual model[J]. International Journal of Project Management, 2008, 26:348~356
[5] Carazo A F, et al. Guerreroa, Rafael Caballer-ob. Solving a comprehensive model for mul-tiobjective project portfolio selection[J]. Com-puters and Operations Research, 2010, 37:630~639
[6] José A,et al. Simulating the dynamic schedu-ling of project portfolios[J]. Simulation Mod-elling Practice and Theory,2010, (18):1428~1441
[7] Senay S,et al. Decision support optimizationof R&D project portfolios under endogenousuncertainty[J]. European Journal of Opera-tional Research, 2010, (207): 420~433
[8] Bai S J,Li S K,Guo Y T. Organizational pro-ject selection based on fuzzy multi-index evalu-ation and BP neural network[A]. 2010 Inter-national Conference on Management and Serv-ice Science[C], 2010:24~26 (In Chinese)
[9] Eppinger S D,Whitney D E,Smith R P,Ge-bala D A. A model based method for organi-zing tasks in product development[J]. Re-search in Engineering Design, 1994, 6(1)
[10] Browning T R. Applying the DSM to system decomposition and integration problems: a re-view and new directions[J]. Engineering Management, 2001, 48(3):292~306
[11] Yassine A. An introduction to modeling and analyzing complex product development processes using the design structure matrix method[J]. Italian Management Review,2004, 9: 134~144
[12] Yonas Nebiyeloul-Kifle. Application of the De-sign Structure Matrix to Integrated Product De-velopment Process,for MBA. Sloan School of Management, 2005
[13] Maheswari J U,Varghese K. Project schedu-ling using dependency structure matrix[J]. International Journal of Project Management,2005, 23(3):223~230
[14] Zhang Y C,Bai S J,Guo Y T. The applica-tion of design structure matrix in project schedule management[A]. 1st International Conference on E-Business and E-Government[C], 2010: 2813~2816 (In Chinese)
[15] Danilovic M, Sandkull B. The use of depend-ence structure matrix and domain mapping matrix in managing uncertainty in multiple project situations[J]. International Journal of Project Management, 2005, 23(3):193~203
[16] Ren L D,Bai S J,Guo Y T. Project schedu-ling in AND-OR Graphs based on design structure matrix[A]. 2010 IEEE Internation-al Conference on Emergency Management and Management Sciences[C], 2010,8:161~164(In Chinese)