MENG Ke-sheng. The Program Research on Security Programs Before Flight Based on Single Code Network Plan[J]. International Journal of Plant Engineering and Management, 2014, 19(2): 110-115

The Program Research on Security Programs Before Flight Based on Single Code Network Plan
MENG Ke-sheng
Anhui Civil Aviation Airport Group,Hefei 230086,P.R. China
Abstract:
The civil aviation industry has made rapid development with the continuous growth of China's economy. At the same time,the airline companies buy more and more civil aircrafts. This phenomenon will lead to a big flying density,which will make airport management become more complex. This paper first introduces the characteristic of security programs before flight and the single code network plan,and then put the security programs before flight into the single code network plan to find out the key route and calculate the guarantee period. Finally,we analyse the programs according to the guarantee period and critical route. It not only provides a support for administrator,but also we present a reasonable methods to reduce the guarantee period.
Key words:    civil aircraft    security programs    network plan    period   
Received: 2014-03-27     Revised:
DOI: 10.13434/j.cnki.1007-4546.2014.0207
Corresponding author:     Email:
Author description:
Service
PDF(475KB) Free
Print
Authors

References:
[1] Wei D S. Differences between activity-on-ar-row network and activity-on-node networkbased on dummy activity [J]. Journal of Chongqing Jiaotong University,2012, 31(4):819-823 (in Chinese)
[2] Chen Z H,Li J H. The research on CAD sys-tem of single code network plan[J]. Wuhan College of Chemical Industry,2006, 28(1):20-22 (in Chinese)
[3] Su Z X,Li X M,Qi J X. Theory and method of creating dual network model in network planning[J]. Journal of Beijing University of Aeronautics and Astronautics,2012, 38(2):257-262 (in Chinese)
[4] Zhang D. The research on project completion probability characteristic of PERT [D].Dalian:Dalian University of Technology,2011(in Chinese)
[5] Zou H,Fang Q, Qiu H L. Reserch on plotting algorithm of extended activity-on-node network diagram[J]. Computer and Modernization,2013, 7:169-171 (in Chinese)
[6] Liu J M. Study on the project schedule optimi-zation method[J]. Journal of Tianjin Universi-ty, 2003, 36(5):610-613 (in Chinese)
[7] Work procedures manual of Department of ground Service of Anhui Civil Aviation Airport Group[M].2014