BAI Li-biao, SONG Hong-yan, BAI Si-jun, GUO Yun-tao. Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix[J]. International Journal of Plant Engineering and Management, 2013, 18(4): 204-211

Resource-constrained Project Scheduling with Overlapping Activities Based on Extended Dependency Structure Matrix
BAI Li-biao, SONG Hong-yan, BAI Si-jun, GUO Yun-tao
School of Management,Northwestern Polytechnical University,Xi'an 710072, P.R. China
Abstract:
Dependency Structure Matrix( DSM) is a successful and powerful tool for representing and analyzing dependencies between the items,but for external influencing factors it cannot charge effectively. This paper sets the stage for connecting the activities and resources,which not only considers information flow but also resources constrains.We first introduce the DSM to represent the degree of overlapping between the activities in a project. Then we present the Extended DSM combined former DSM and resource factors to calculate the project duration. Finally,the practical significance of the Extended DSM is confirmed by an illustrative example.
Key words:    overlapped    Extended DSM    resource constraint    project duration   
Received: 2013-08-10     Revised:
DOI:
Funds: The paper is supported by the National Natural Science Founda-tion of China under Grant No. 71172123,the Aviation Science Fund under Grant No.2012ZG53083,the Soft Science Founda-tion of Shaanxi Province and the funds of NPU for Humanities and social sciences and management revilization under Grant No. RW201105
Corresponding author:     Email:
Author description:
Service
PDF(278KB) Free
Print
Authors

References:
[1]Roy G,Nava P,Isrel S. Integrating system a-nalysis and project management tools[J]. In-ternational Journal of Project Management,2002, 20:461-468
[2] Yassine A,Falkenburg D,Chelst K. Engi-neering design management: an information structure approach[J]. Int. J. Prod Res.,1999, 37(13):2957-2975
[3] Browning T R. Applying the design structure matrix to system decomposition and integration problems: a review and new directions[J].IEEE Transactions on Engineering Manage-ment,2001
[4] Chen C,Ling S F,Chen W. Project schedu-ling for collaborative product development u-sing DSM[J]. International Journal of Project Management,2003(21):291-299
[5] Guo Y T,Xu J C,Bai S J. Project scheduling with overlapping activities using dependency structure matrix [C]// Proceedings of the 14th International Conference on Industrial Engineering and Engineering Management,Vols a and B-Bulding core competencies through IE & EM,2007:1167-1172
[6] Eppinger S D,Whitney D E,Smith R P,Ge-bala D A. A modelbasedmethod for organizing task in product development[J]. Des,1994,6(1):13
[7] Browning T R. Use of dependency structure matrices for product development cycle time reduction[C]// Proceedings of the Fifth ISPE International Conference on Concurrent Engineering: Research and Applications,To-kyo,Japan,1998
[8] Maheswari J Uma, Varghese K. Project schedu-ling using dependency structure matrix[J]. In-ternational Journal of project Management,2005, (23):223-230
[9] Steward D V. Systems analysis and manage-ment: structure, strategyand design [M].Princeton: Petrocelli Books,1981
[10] Chen Chun-Hsien,Ling S F,Chen W. Pro-ject scheduling for collaborative product de-velopment using DSM[J]. International Jour-nal of Project Management,2003, (21):291-299
[11] Tang R Z,Ding X H,Zhou G M. Study on the rearranging management of the informa-tionization implementation processes of enter-prises[J]. Journal of Zhejiang University,2002, (4)(in Chinese)